HomeMy WebLinkAboutFIN-08-103 - E08-061 - Engineering Services - Electrical/Mechanical - Consolidated Maintenance Facility~. a' REPORT Report To: Mayor Carl Zehr and Members of Council Date of Meeting: 2008-08-18 Submitted By: Larry Gordon Prepared By: Larry Gordon Date of Report 2008-08-06 Report No: FIN 08-103 Subject: E08-061 -Engineering Services -Electrical /Mechanical -Consolidated Maintenance Facility RECOMMENDATION That Expression of Interest E08-061, Engineering Services -Electrical /Mechanical - Consolidated Maintenance Facility, be awarded to Morrison Hershfield Limited, Burlington Ontario, at their estimated fee of $730,012.50, including disbursements and G.S.T., based on a satisfactory contract being negotiated and an upset fee being established, and further that the Mayor and City Clerk be authorized to execute an agreement satisfactory to the City Solicitor. BACKGROUND The City of Kitchener is in the process of developing an existing building and industrial property at 131 Goodrich Drive to become the City's Consolidated Maintenance Facility. The services of an Electrical /Mechanical Engineering Firm are required. The building will be primarily a huge vehicle repair garage with other incidental uses. The equipment that exists in our present repair garages will either be relocated, or new equipment will be procured, to provide the same level of service or better. In essence, the mechanical / electrical consultants will prepare tender packages to provide the existing equipment in the newly purchased building. The building's main HVAC equipment and electrical distribution network needs to be designed and tendered. Upgrading of the existing sprinkler system to comply with the new design is required. Engineers will assist the Project Manager in controlling costs by budgeting for the work under their purview. There is potential that we install weigh scales and a fueling depot; therefore, we would need to supply power and mechanical features which would also form part of the engineer's work. We will definitely need to provide standby power. Engineers will participate in the efforts to determine size and associated costs of the standby generator and switch gear. Upgrading of the security system and voice data wiring forms part of the work. REPORT In accordance with Chapter 170 Professional Services/Consultants, established consisting of L. Proulx, Operator, and S. Rudak, Buyer. of the Municipal Code pertaining tc an Engineering Services Review Director of Facilities Management, P. the Selection of Committee was Christner, Building Expressions of interest were advertised in the Record, on the City of Kitchener Home Page and the Internet through the Ontario Public Buyers Electronic Tendering Information System relative to this project. Documents were downloaded by six (6) interested parties. By the closing date of Friday July 4t", 2008, four (4) responses had been received. The Review Committee met on Friday July 11t", 2008 to review the submissions. A shortlist of two (2) Engineering Firms was selected for further interviews. The Review Committee met on Friday July 25t", 2008 to interview the shortlisted candidates. The Committee elected to award the project to Morrison Hershfield Limited, Burlington, Ontario. A listing of the responding parties follows for your reference. Morrison Hershfield Limited, Burlington Giffels Associates Limited, Toronto ECE Group, Toronto The Walter Fedy Partnership, Kitchener FINANCIAL IMPLICATIONS Funding will be provided from index 526073 and 528000 -Central Maintenance Facility REVENUES Contribution from Capital $22,637,523. Contribution from Reserve $ 330,000. Contribution from Gas $ 1,560,000. Contribution from Water $ 1,560,000. Contribution from Sewer $ 1,560,000. Contribution from DC $ 3,299,000. Land Sales $14,650,000. Existing Capital Funds 428 000. TOTAL $46,024,523. EXPENSES Land Costs Consulting E08-061 $730,012.50 Less G.S.T. Rebate ($ 34,762.50) $695,250.00 Consulting People Amalgamation Art Miscellaneous (Fees & Permits) Building Alterations Relocation Costs Information Technology System Contingency Interest Costs TOTAL Deficit * The project is currently under funded by $2,185,811. At the Corporate Services Committee, it was resolved that staff planning phase, once designs and costs have been finalized. ~- $22,410,308. $ 1,701,961. $ 695, 250. $ 200, 000. $ 200, 000. $ 106, 527. $18,000,000. $ 300, 000. $ 300, 000. $ 2,300,000. 1 996 288. $48, 210, 334. $ 2,185, 811. November 19, 2007, Finance and deal with this deficit through the Larry Gordon Director of Purchasing T O ~ DD W V O 0 LL ~ ,~ ~ N c~~~o ~ ~ ~ c°v i ~ 0 N •~ ~ M _~ .~~~ 3 ~ c~X~ ~ ~ ~ ~ i~V?Q N~ V O 0 0 0 0 0 0 0 0 0 0 O O Q ~ ~ p ~ O ~ ~ ~ LL ~ .~ ~ ~ N ~~~~~~~ 00000000 ('~ OOrOOf~000000 ~ r p+~ N0000000 N OrOON000000 C'~ r ~ ~ Ln0000000 ~ C'~NOOLn0000N C'~ 00 • f~00000000 ~ OI~OOCOOOOOCO O l!~ p ~ t'~C'~tDCOtDOLnN N x000000000 r 00 ~ COC")LnLnLnNCO~ ~ O ~C")NNrOC7C'7C'~O N r rrxC'~~ CV tD NN 00 Nx OO N N ~..~ .~ ~. x .~ .~ ~ N x ~ ~ i ~ O O O O ,' p ~ ~ N N N '! ~ rn ~ ~ c~ c~ c~ ~ p O 000000 O OOOOOc~000000 0 O -+r O 000000 0 ONOO~000000 ~ f~ ~ ~ • O 0000000 ~ ~ NNN~00 00 ~ OOOOOc~0000N ~NOOOOOOOOtD ~ x In (D p L N xxxl~Ln~ C'7 O(~00000000 ('7 0 ~ 0 ('~C'~C'~N(Dx .~ .~ .~ 0 xNNN OC7C7C'~0 f~ f~ .. O N x ~ O r 00 CV r ~ 00 N `-' x .~ .~ C'7 N x ~ ~ ~ ~ ~ 00000000 C'7 ' 000'~00~00000 ' ~ 0 ~ U NOOOOOOx Ln000000x C 7 (~ OC ~ 00 (fix x N C4 O O Q N O 00 00 00 ~ O 00 0 CO 0 00 ('0 Cfl xC'~~~~NOf~ 00 OCO 00 O f~(~NNNOON O ('0~ f~ ('7 T x x x x~ `i ~i `i `i ~i ~i O x N N `i ~ p 00000 O Nr0 f~0 O O O O ~ 00000 O (Dr0 NO O O O ~~ 00000 O NNO LSO O O O ~ m OO OO OO Ln 0 0 L~ f~ 0 (D O O O 0 ~~~NO (D (D00 00 O O (D N N N O In N ~ O x x O N ~ N T T T T O ~ ~ ~ V N ~~ °' ~ ~ cn 0 a ~ ~ c~ N ~ N ~ ~ ~ ~ ~ N~~ N ~ ~ c U ~ v Q cn 0 UOCC~~cnD ~ a~a~ ~c ~ ~~ o ~oN~ 0 0 0 0 0 0 ~ N L p N~ N p ~ p v /•~ N Q~ ~ U ~ N p ~ C C~ C~ N~ ~ N O ~ U 0 0 0 0 0 0 a"' 0 0 N ~ p p U ~ ~ Q 0 N +~ + + +~ +~ +~ N N c c C O N V Q ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ U ~ ~ ~ c W N U ~ ~ ~ }, N ~ ~ N N ~ 0= ~ ~ +~ ~ ° V ~ ~~ c c~ c c ~.N m~ c c o~~ ~ o v C m o ~ ~UUUUUU UUQ ~o ~ ~ O ~W ~ ~ ~ a ~ ~ w N O N N (~ p E 0 U N .; N N c~ Q U ~~ c ~ ~ N p ~ U ~ C (~ ~ C LL N ~ N O ~ O N ~ 0 ~ T (f~ ~ O N U N ~ O N (j Z ~_ ^~ p •(~ W ~ ~ Q U •~ T Q ~.i TM /~' W A C 00 ~ (~ T n W ^ '~ i1 .~ ~ /~~ /'1 ~{ ~ A `U ~ ~..r ^~^,, W ~ ~ O -_ ~ L N+~~_ N ~ U ~_ ~ N U ~ ~ X U N ~ N~ N~~ U L O p ~_ L •O ~ ~ ~ ~ ~ (~ m~ ~ ~ ~ zZ ~