Report To: Mayor and Members of Council
Date of Meeting: January 26, 2009
Submitted By: Grant Murphy, P.Eng. Director of Engineering Services
Prepared By: Steve Allen, P. Eng., Manager, Enginering Design and
Approvals
Ward(s) Involved: Ward 1 & 6
Date of Report: January 21, 2009
Report No.: DTS 09-019
Subject: KING STREET & THE CITY CENTRE DISTRICT:
CONTRACT AWARD REVISION -AMENDMENT TO FIN 08-
154
RECOMMENDATION:
That the award for tender T08-015 approved at the December 8, 2008 Council meeting, be
increased by $2,058., for a revised total of $7,599,224., including contingencies and GST,
to correct a mathematical error.
BACKGROUND
Tender T08-015, King Street - Frederick/Benton Street to Francis Street and Speakers Corner
- Road and Streetscape Construction was awarded at the December 8t", 2009 Council meeting
through a recommendation in report FIN 08-154. After the award, a mathematical error of
$2,058. was noted in the tender award amount. This recommendation is to correct the error.
FINANCIAL IMPLICATIONS:
Council report FIN 08-154 projected adequate funding for all projected costs of the King Street
Streetscape project. The minor adjustment of $2,058 to the construction tender can be
accommodated by the contingency within the construction contract.