HomeMy WebLinkAboutDTS-09-055 - King St & Speakers Corner ReconstructionDevelopment&
Techrrica~ Services
Report To: Council
Date of Meeting: March 30, 2009
Submitted By: John McBride, Director of Transportation Planning
Prepared By: Stephanie Brasseur, Traffic Project Co-ordinator (741-2373)
Wards}Involved: Ward 1 -Bridgeport -Center
Ward 6 -West -Victoria Park
Date of Report: March 24, 2009
Report No.: DTS-09-055
Subject: KING STREET AND SPEAKERS CORNER
RECONSTRUCTION-FREDERICK/BENTON STREET TO
FRANCIS STREET -NOISE EXEMPTION
RECOMMENDATION:
That the City of Kitchener and its contractor(s) be exempt from the provisions of Chapter
450 Noise of the City of Kitchener Municipal Code Article 6 Construction Work during the
King Street and Speakers Corner Reconstruction project in the City of Kitchener. The
request for the noise by-law exemption is for between the hours of 7:00 p.m. and 7:00
a.m. for the period April 6, 2009 to September 30, 2009.
BACKGROUND:
The City of Kitchener contract for the King Street Streetscape will commence on April 6, 2009
and is anticipated to be completed by the end of September, 2009. This project includes the
following planned work:
• Municipal services -water services, gas services
• Private Enterprise services -Hydro, Cable, Telecommunications
• Street lights
• Roadway surface
• Curb and gutter
• Sidewalks.
4-1
REPORT:
In order to complete the work and minimize disruption for the King Street businesses and
complete the necessary improvements, extended hours and weekend work must take place to
complete the project in the time allotment. This exemption is requested to complete certain
operations of work to mitigate the impact of construction.
For example, the present work that is proposed to date for after hours work includes, but is not
limited to:
• Watermain servicing and hydrant relocation will be completed early in the project and will
entail work after hours when businesses are closed during the approximate times of 2:00
a.m. to 6:00 a.m. Prior to commencement, this work will be communicated by letter to all
businesses and residents that will be directly affected. These times were chosen in
order to minimize the impact on adjacent businesses and their operations.
SCOPE /STAGING OF WORK:
There are several stages to the King Street Streetscape (copy attached). The staging of the
work proposed for 2009 includes:
Stage 1: Gaukel Street to Ontario Street (south side)
Stage 1 b: Speakers Corner
Stage 2: Ontario Street to Queen Street (south side)
Stage 3a: Queen Street to Frederick / Benton Street (south side)
Stage 3b: Frederick / Benton Street to Queen Street (north side)
Stage 4: Queen Street to Ontario Street (north side)
Stage 5: Gaukel Street to Frederick / Benton Street (south side).
In general, the scope of this project includes the following planned work:
• Municipal services -water services, gas services
• Private Enterprise services -Hydro, Cable, Telecommunications
• Street lights
• Street trees /landscape planters
• Roadway surface
• Curb and gutter
• Sidewalks.
TYPEOF NOISE:
The majority of the noise will be created by the removal of concrete and services along with
excavation of the sidewalk area in order to complete the work. During the road works, the use
of a milling machine and paving equipment will be used to resurface King Street. This work will
be undertaken during permitted working hours (7:00 a.m. to 7:00 p.m.). The road works will be
completed at the end of the project, once the sidewalks are complete. There may be extended
work hours implemented in order to accommodate an increased work schedule in each stage of
the work. Concrete pours will be scheduled beyond regular working hours where necessary to
address concerns for business access during business hours to entrances directly onto King
Street.
4-2
These additional hours of permitted work are requested to allow for the most impactful work
operations to be conducted during the hours of 7:00 a.m. to 7:00 p.m., allowing for less
impactful operations such as preparation work, forms preparation and removal and general site
clean up to be completed outside of these hours. This less impactful work will not commence
before 6:00 a.m. and is expected to go no later than10:00 p.m.
Noise protocol will be followed, which covers administrative measures such as scheduling of
noisy activities at times of least impact, selection of haulage routes to minimize close proximity
to neighbours, and maintaining contact with residents.
Additionally, the City of Kitchener and their consultant have advised that any changes to the
work schedule proposed by the contractor will be addressed on its own merits and that any
additional noise impacts outside of the permitted hours will require further approval by the
project team and as such, detailed communication will be provided to residents and businesses
along King Street.
In order to expedite the construction and allow extended hours of work to take place for this
project, thereby minimizing traffic impacts, we recommend that this request for a noise by-law
exemption be granted.
DURATION:
Regular working hours will include and are permitted 7:00 a.m. to 7:00 p.m. Monday to
Saturday; however the Contractor is requesting to work extended hours when required to
complete work sensitive to traffic issues and to benefit the project timelines. Regular extended
hours will include 7:00 p.m. to 7:00 a.m. Monday to Saturday in order to reduce impacts of
business operations. Sunday work may occur between 8:00 a.m. to 5:00 p.m. and would be
limited to general clean up and preparation work where formal inspection would not be
necessary. Sunday work is a possibility for paving, but inspection would be required for this
operation.
All additional work will be assessed by City staff for allowing extended hours and will be defined
as a benefit to the project. Council will be notified at least a minimum of 48 hours in advance of
the work as the need arises.
FINANCIAL IMPLICATIONS:
None. Provisions have been included in the contract, encouraging the contractor to complete
this work as soon as reasonably possible.
COMMUNICATIONS:
The City of Kitchener and its contractor will communicate the expectation of extended working
hours to area residents l businesses and have been actively advising of any changes as they
develop. Communication updates will be provided on a regular basis.
4-3
~~NLUI~N:
In order to expedite the construction and allow extended hours of work to take place for this
project, thereby minimizing-disruption and impacts al: oonstr~ction on ~usinees I residents, eve
recommend that this requetfara noise by~lawexemption be granted.
John P. ~IIIcBride, Director
Transportation Planning
l~O ~ ~
~te~hanie Brasseur, . E.T.
Traffic Project o-ordinatar
Transportation Planning
B
Attachment:
~i ~ ~ ~~
Ken Carmichael, .E~T~
supervisor of Traffic 8~ Parking
Transportation Planning
4-4