REPORT NO.: DTS-09-167
SUBJECT:
Development Charges - Engineering Services Cash Flow
Adjustments
RECOMMENDATION:
THAT the Development Charges capital project timing adjustments outlined in Table 1 to staff
report DTS-09-167 be made to in the 2010-2019 capital forecast to reduce the projected 2010
Engineering Services reserve fund deficit, subject to final budget deliberations
BACKGROUND:
Staff has reviewed the proposed timing of Engineering Development Charge (DC) funded
projects against the cash flow projections within the DC Reserve Fund. The findings of this
review are attached to this report, along with recommendations to Council for consideration as
part of the capital budget presentation.
REPORT:
Current projections within the Engineering Services portion of the DC reserve fund indicate that
the fund will be in deficit in the amount of $12.8 million by the end of 2010 (contrasted with a
projected 2009 ending surplus of $8.0 million). The deficit will be significantly larger if the recent
declining trend in development activity persists into 2010. This is compounded by an existing
deficit in the Non-Engineering portion of the reserve fund, largely resulting from the construction
of Fire Station #7 and the Activa Sportsplex, the costs of which are being recovered through
future development charges. Assuming that only 50% of the growth forecast materializes in
2010, the Engineering Services deficit could be as high as $16.6 million and the total deficit
could reach $26.2 million.
In light of the risks associated with incurring a significant deficit in the DC reserve fund,
especially in a period of economic uncertainty, staff has identified the following Engineering
projects for adjustment in 2010 to reduce the extent of the deficit:
Table 1: Proposed Adjustments (in $000’s)
PROJECT NAME 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019
(306) (312) (318) 306 312 318
Intensification Allowance
Borden Greenway Trunk Sewer (139) 139
(2,116) 2,116
Freeport Pumping Station Upgrade
(492)492
Pioneer Tower Pumping Station Upgrade
(492)492
Falconridge Pumping Station Upgrade
Laurel Creek Watercourse (259)
Schneider Creek Channel (620) 620
City Share of Subdivisions (255) (260) (265) 780
Blockline Rd. East (5,000) 5,000
Hwy 7 Ext'n - secondary watermain (629) 629
èÍÈÛÐìÊÍÌÍÉ×ØùÔÛÎÕ×É
Forecast Engineering Services Reserve
Ending Balance (12,825) (10,898) (12,217) (18,860) (25,647) (22,545) (20,582) (17,080) (11,507) (41,715)
Revised Forecast Engineering Services
Reserve Ending Balance, if above
(2,576) (7,687) (9,286) (16,920) (23,948) (21,102) (19,081) (16,161) (10,551) (40,457)
changes made
Refer to Appendix “A” for detailed descriptions of each of the projects listed above. The order
of the projects is not indicative of relative priority.
FINANCIAL IMPLICATIONS:
The proposed DC project deferrals will reduce the projected deficit in the reserve fund in 2010
and eliminate the requirement for debt financing in a period of uncertain economic growth.
Appendix “A” - 2010 Development Charges Capital Project Scope Documents
ACKNOWLEDGED BY: Jeff Willmer, General Manager, Development and Technical Services
PROJECT SCOPE REPORT
Proram Name:Intensification Allowance
g
Location:Identified in the DC Background Studies
Nature of Work:
Existing sewer, water and road infrastructure will be replaced due to additional capacity
requirements due to intensification associated within the central neighborhoods area.
This work will be typically integrated as part of the City's accelerated infrastructure
replacement program.
Justification of Work:
This account is used to upgrade engineering services due to the intensification within
central neighbourhood areas, as identified in the DC background studies.
Notes:
Due to D/C fund cashflow constraints, funds were re-allocated from 2010, 2011, and
2012 to 2013, 2014, and 2015, respectively.
Proram Name:Borden Greenway Trunk Sewer
g
Location:South of Ottawa Street South to just north of Ottawa Street South
Nature of Work:
(1) An Environmental Assessment for a new trunk sanitary sewer, (2) The construction of
a new trunk sanitary sewer.
Justification of Work:
The Borden Greenway Trunk Sanitary Sewer for a short section from 46 metres south of
Ottawa Street South to a manhole just north of Ottawa Street South must be upgraded in
order to accommodate the ultimate flows from areas west of Westmount Road. An
Environmental Assessment Study will be required to determine the preferred method of
achieving sanitary sewer upgrades.
Notes:
Awaiting the completion of the city-wide sanitary capacity study. This project has been
deferred to 2011.
PROJECT SCOPE REPORT
Program Name:Freeport Pumping Station Upgrade
Location:
3563 KingSt. E. across from the Freeport Hospital
Nature of Work:
(1) Capacity and infrastructure analysis (2) Environmental Assessment for a sanitary
pumping station and force main (3) Construction of a sanitary pumping station and force
main.
Justification of Work:
The City requires that the existing pumping station and infrastructure be evaluated and
upgrades determined. An EA will be required to determine the improvements.
Notes:
The City has completed its capacity and infrastructure analysis, and currently
undertaking an Environmental Assessment. Design work is to be completed in 2010 and
construction will begin in 2011.
Program Name:Pioneer Tower Sanitary Pumping Station Upgrade
Location:Pioneer Tower Road
Nature of Work:
(1) An Environmental Assessment for an upgraded sanitary pumping station, (2) The
construction of a sanitary pumping station.
Justification of Work:
The City requires that the existing pumping station be upgraded to accommodate
planned future development.
Notes:
Due to D/C fund cashflow constraints and no imminent development requirements in the
area this project has been deferred from 2010 to 2012.
PROJECT SCOPE REPORT
Program Name:Falconridge Sanitary Pumping Station Upgrade
Location:
Falconridge Drive
Nature of Work:
(1) An Environmental Assessment for an upgraded sanitary pumping station, (2) The
construction of a sanitary pumping station.
Justification of Work:
The Falconridge Sanitary Pumping Station requires upgrades to service future
development within the catchment. An Environmental Assessment will be required.
Notes:
Due to cashflow constraints and no imminent development requirements in the area this
project has been deferred from 2010 to 2012.
Program Name:Laurel Creek Watercourse
Location:Lower Laurel Creek from Bridge Street to City Of Kitchener limits
Nature of Work:
(1) A revision of an Environmental Assessment for the improvement of the Laurel Creek
watercourse, (2) Watercourse improvement.
Justification of Work:
In 1995, the Grand River Conservation Authority finalized the Slope Stabilization and
Erosion Control Class Environmental Assessment for the Lower Laurel Creek between
the Grand River and City of Kitchener Municipal boundary. A portion of this creek was
upgraded in accordance with this plan. The cost of the remaining areas from just east of
Bridge Street to the City Boundary have been estimated so that 90% is applicable to
capital costs and 10% is applicable to development charges.
Notes:
Due to D/C and C/C fund cashflow constraints this project has been deferred from 2019
to 2020.
PROJECT SCOPE REPORT
Program Name:Schneider Creek Channel
Location:
Manitou Drive to Hayward Avenue, Balzer Road, Homer Watson Blvd
Nature of Work:
(1) Environmental Assessment (2) Watercourse work between Manitou and Hayward (3)
Watercourse work from Homer Watson to the Grand River.
Justification of Work:
In 1995 Paragon Engineering Limited finalized the Schneider Creek Remediation Class
Environmental Assessment, Environmental Study Report for Schneider Creek between
Manitou Drive and Hayward Avenue under the direction of the Grand River Conservation
Authority. This Environmental Assessment will have to be updated to reflect current
practice for rehabilitating this stream. An estimate for a preferred alternative has been
provided, including the installation of new culverts at Balzer Road and the railroad line. It
is also proposed to undertake remedial work on the creek from Homer Watson Boulevard
to the Grand River due to extensive erosion problems.
Notes:
EA amendment and detail design to being in 2010. Consturction commencing in 2011.
Program Name:City Share of Subdivision Works
Location:Various
Nature of Work:
Possible projects include road widening and the installation of new sidewalks on
backlotted arterials.
Justification of Work:
It has been the practice of the City to set aside monies from the Development Charge
Fund for the City's share of works to be done in subdivisions or adjacent thereto.
Notes:
Due to D/C fund cashflow constraints, funds will be re-allocated from 2009, 2010, and
2011 to 2012, 2013, and 2014, respectively.
PROJECT SCOPE REPORT
Program Name:Block Line Road East
Location:
Block Line Road from Homer Watson Boulevard to Courtland Ave
Nature of Work:
(1) Road extension (2) New bridge construction
Justification of Work:
It is proposed that Block Line Road be extended from Homer Watson Boulevard to
Courtland Avenue.
An Environmental Assessment was completed by the City in May 2001 and the first
section of road from Homer Watson Boulevard to Hanover Street has been completed.
The remaining stretch of road from Hanover Street to Courtland Avenue across
Schneider Creek and the Railway Yards requires a bridge. The detailed design of the
portion of the road from Hanover to the Hanson Avenue extension has been completed.
Notes:
The Region is currently working on the design for the LRT, which has delayed design
work for Block Line Rd. The construction for Block Line Rd will begin at the end of 2010
with completion scheduled in 2011.
Program Name:Highway 7 Extension - Secondary Watermain
Location:From Shirley Ave to Bridge Street
Nature of Work:
The construction of a 300mm diameter watermain, valvues and hydrants, 450mm
crossing of Grand River, connections and commissioning.
Justification of Work:
For security of water supply into the Bridgeport Area a secondary watermain connection
is necessary. An additional benefit of this connection will be an increase in water
circulation and therefore water quality can easily be maintained. This main is to be
installed at the time of the construction of a new Highway 7 Grand River crossing. The
main is approximately 1900 metres in length and 300 millimeters in diameter, and it is
anticipated that six valves will be needed.
Notes:
There is no imminent development potential at this time. This has been deferred from
2010 to 2017.