HomeMy WebLinkAboutKPL - Report - Central Library Funding PlanREPORT
Report To:
Councillor Berry Vrbanovic, Chair and Members of Finance and
Corporate Services
Date of Meeting:
November 23, 2009
Submitted By:
Kitchener Public Library Board
Prepared By:
Sonia Lewis, CEO, Kitchener Public Library
Ward(s) Involved:
All
Date of Report:
November 11, 2009
Subject:
CENTRAL LIBRARY FUNDING PLAN
______________________________________________________________________
RECOMMENDATIONS:
THAT the fundraising contribution to the Central Library renovation and expansion project be
reduced from $4,000,000 to $500,000; and,
THAT the reduction in fundraising be offset by an increase in the development charges allocation to
the project from $528,000 to $4,028,000; and,
THAT these adjustments to the central library capital project be included in the 2010-2019 capital
forecast for consideration by the Finance and Corporate Services Committee as part of the 2010
budget deliberations; and,
THAT $266,400 allocated to Main Library roofing in the approved 2009 capital budget be transferred
to the central library project to be used for roofing; and further,
THAT City Council express its intention to recover 90% of the post 2018 growth-related costs of the
Central Library renovation and expansion through development charges in the future and as
committed excess capacity under the Development Charges Act.
BACKGROUND:
At its October 6, 2008 meeting Council approved a preliminary capital budget and the following
funding strategy for the central library renovation and expansion project:
1
Approved Central Library Funding Strategy
Funding Source Funding
Economic Development Investment Fund$32,500,000
Fundraising$4,000,000
Deferral of Other KPL Capital Projects $1,150,000
Development Charges $528,000
Province’s Investing in Ontario Grant or Other $1,634,000
Capital Dollars
Total Funding $39,812,000
The funding plan was based on an analysis of eleven potential funding options outlined in FIN-08-
097.
The fundraising target was established on the basis of a fundraising feasibility study undertaken in
2005. The study measured support for the construction of a new 130,000 square foot library on
Centre Block, rather than the renovation of the existing library.
The development charges revenue reflected a preliminary analysis done prior to the 2009
development charges background study. At its meeting held October 6, 2008 Council directed City
Finance staff to include forecast growth-related expenditures for a central library in the 2009
development charges background study.
The approved 2009-2018 capital budget and forecast included $270,000 in 2009 for Main Library
roofing. Since it was anticipated the work would be completed in 2009, costs for this section of
roofing were excluded from the central library project budget.
This report proposes revisions to the approved funding strategy for the central library renovation and
expansion project and the transfer of funds for roofing in the approved 2009 capital budget to the
central library project.
REPORT:
The approved funding strategy for the central library project includes funds from a number of
sources, including fundraising and development charges. The Kitchener Public Library Board
proposes reducing its fundraising target and offsetting this reduction with development charges.
The central library funding plan approved by Council October 6, 2008 assumed fundraising would
contribute $4M to the project. This target was based on a fundraising feasibility study undertaken in
2005 during the Centre Block project.
Given changes in the economy and the plan to renovate, rather than build a new facility, a second
fundraising feasibility study was conducted earlier this year. This study concluded there is no
evidence to support a $4M (net) campaign and recommended a target of $500,000 be raised over
five years. Factors limiting KPL’s ability to fundraise at the $4M level include:
- the economic climate
- donors being more likely to support local charities in tough economic times
- the perception that libraries are the responsibility of government and since government is
paying the major portion of the cost, taxpayers should not be asked to pay twice
- KPL not having a culture of fundraising or a committed major gifts donor base
2
At the direction of Council, forecast growth-related expenditures for a central library were included in
the 2009 development charges background study. A second library building project, the southwest
community library, was also included. The study indicated a higher funding envelope would be
available for these growth-related library projects than originally projected.
The maximum allowable funding envelope for 2009-2018 totals $12,711,930 in 2009 dollars. Library
services are considered by the Development Charges Act to require a 10% reduction in their capital
cost recovery, leaving $11,440,737 in 2009 dollars in development charges revenue for library
projects. After adjustments to the development charges to reflect inflation, the Board proposes
allocating $4,028,000 of this amount to the central library project. The remainder would be available
for the southwest branch.
The 2009 Development Charges background study identified that additional costs related to the
Central Library renovation and expansion totalling $6,067,591 in 2009 dollars may be recoverable
after 2018 since the project will support growth beyond the next ten year window. In order to recover
these costs, Council must state its intention to recover 90% of the post 2018 growth-related costs
through development charges in the future and as committed excess capacity under the
Development Charges Act.
The approved 2009 capital budget included $270,000 to replace the oldest sections of the Main
Library roof. Based on the age and condition of these sections, KPL had been advised not to delay
this roofing until the central library renovation. Earlier this year, architects working on the central
library project indicated our 2009 roofing plans would present challenges in achieving LEED Gold for
the renovation and expansion project. As a result, emergency patching was applied to the roof at a
cost of $3,600 and the remainder of the work delayed. Further patching may be required over the
course of the next couple years and any such costs will be covered by the Library’s general
provision funding. Since we anticipated completing this work in 2009, costs for this section of roofing
were excluded from the central library project budget. The KPL Board proposes transferring the
remaining $266,400 in the 2009 capital budget for roofing to the central library project. The funds
will be used for their original purpose.
FINANCIAL IMPLICATIONS:
No new funding is being requested. Council previously approved $270,000 for roofing in 2009 and a
funding strategy totalling $39,812,000 for the central library project. A reduced fundraising target,
increased development charges allocation, and transfer of the unspent 2009 capital funds for roofing
result in the following revised central library project funding plan:
Funding Source Original Central Adjustment Revised Central
Library Plan Library Plan
Economic Development Investment $32,500,000$32,500,000
Fund
Fundraising $4,000,000($3,500,000)$500,000
Deferral of Other KPL Capital $1,150,000$1,150,000
Projects
Development Charges $528,000$3,500,000$4,028,000
Other Capital Dollars $1,634,000$1,634,000
Unspent 2009 Capital for Roofing $0$266,400$266,400
Total Funding $39,812,000$266,400$40,078,400
The project has been budgeted on this basis in the 2010 forecast.
3
COMMUNICATIONS:
KPL continues to keep stakeholders informed of the progress of the project using various
communication tools, including the KPL web site, In Touch magazine, electronic and print
newsletters, displays, and public meetings.
Public consultation on the schematic design was conducted at the Main Library November 3 and at
the Kitchener Market November 7, 2009. In addition, the plans are on display at the Main Library
and on the KPL web site.
Council representatives on the KPL Board receive monthly progress reports on the project. The KPL
Board will report formally to Council when decisions regarding financial matters are required, such
as contract and tender awards.
CONCLUSION:
A viable funding strategy is critical to the success of the central library project. The original
fundraising target of $4M established by the Kitchener Public Library is no longer obtainable given
the current economic climate. As a result, a new target of $500,000 is proposed. The reduced
fundraising target can be offset by development charges.
Roofing is an important component in the Library’s plans to achieve LEED Gold for its renovation
and expansion project. Transferring the unspent funding for roofing in the 2009 capital budget will
help us reach the LEED Gold target.
ACKNOWLEDGED BY: Sonia Lewis, Chief Executive Officer, Kitchener Public Library
4