HomeMy WebLinkAboutDTS-10-034 - King St reconstruction project updateJ KrTC~r~R Financial Services REPORT T0: Councillor C. Weylie, Chair, and Members of the Development and Technical Services Committee DATE OF MEETING: February 8, 2010 SUBMITTED BY: Grant Murphy, Director Engineering Services PREPARED BY: Eric Saunderson, Project Manager, Engineering Construction Jim Oakley, Manager, Engineering Construction WARD(S) INVOLVED: Ward 1 and 6 DATE OF REPORT: January 28, 2010 REPORT NO.: DTS-10-034 SUBJECT: RECONSTRUCTING KING STREET -INFORMATION REPORT RECOMMENDATION: For information. BACKGROUND: "Reconstructing King Street" is an innovative streetscape project aimed at stimulating an economic regeneration in downtown Kitchener. The streetscape enhancements target many of the root causes that have prevented economic revitalization -improved aesthetics, improved lighting and a more livable urban environment. It is anticipated that these enhancements will help to stimulate increased commercial activity, increased office employment and the redevelopment of large vacant parcels, while helping local businesses attract and retain highly qualified employees. On December 10, 2007, a 60% design package and business case (Report No. DTS 07-188) for the reconstruction of King Street and Speakers Corner was presented to the Development and Technical Services (DTS) Committee for its consideration. At that time, DTS Committee endorsed the 60% design which was later ratified by Council of the whole on February 4, 2008, as part of the City's broader capital budget process. Towards the end of the tender preparation process, it became evident that the project budget would be exceeded by a significant margin, due to the use specialized materials, an ambitious construction schedule and the uncertainty of unique design items. In an attempt to gain a better understanding of the cost projections staff completed a detailed design cost estimate prior to releasing the tender packages. On April 7, 2008, the findings of this review were presented to Council of a whole (Report No. DTS 08-052) where, a recommendation was brought forward that requested "staff be directed to pause the timing of construction on the King Street streetscape in order to complete a value engineering assessment." 6-1 The value engineering assessment on the project design concluded; the validation of the current cost estimate by a certified quantity surveyor; and, the development of options that would look at adjustments to the design and the quality of materials being used as a way of lowering the overall project cost before proceeding with construction. In the end, the value engineering assessment provided a greater degree of confidence in the anticipated costs of the project while finding ways to reduce the overall project cost to coincide with the budgeted amount, previously approved by Council. Following the value engineering assessment, staff reconsidered the streetscape design and developed design options to be included in the contract documents / drawings. A revised tender package was issued during the last quarter of 2008. Tenders were issued to six (6) prequalified general contractors, and upon closing on Tuesday November 25th, 2008, four (4) tenders had been received. Steed and Evans Limited (S&E) submitted the lowest bid at $9,105,466.98, although subsequent to tender closing, the scope of the project was adjusted and a revised tender value was recommended to Council on December 8, 2008 (Report No. FIN 08-154). In 2009, the first phase of the construction was completed on King Street (Young / Gaukel Streets to Frederick I Benton Streets) and Speakers Corner between April and September 2009. Through additional funding provided by federal government in the summer of 2009, the scope of project was increased and construction has continued around City Hall on Young, College and Duke Streets. This work has recently subsided due to the weather and is scheduled to resume in late March of 2010. REPORT: The intent of this report is to provide a summary on the status of construction completed to date on King Street, Speakers Corner and the streetscape around City Hall. In addition, this report will provide some insight on the staging of work planned for 2010 and the next steps to be completed on this project. Staaina of Work and Project Schedule On January 21, 2010, City staff received a request from the contractor, S&E, to consider a proposal on the project schedule and staging of work planned for construction on King Street in 2010. As noted in the tender documents (T08-015), the recommended project schedule complies with the anticipated start date of April 5, 2010, and completion date of mid-late September (and/or 110 working days total). And similar to the staging of work methodology completed in 2009, S&E have recommended that the sequence of construction be completed in the same manner and approach. This approach includes the work to be completed on a block by block basis, both sides of the street at a time, with the focus on the curbs, parking, landscape area first, and second, the section of sidewalk along the building faces. The staging plan for this approach includes; Stage 1 a: Young Street to College Street (late March /early April to early June) Stage 1 b: College Street to Water Street (May to July 9, *road reopened for "Cruising on King") Stage 2: Water Street to Francis Street (July to September, *road reopened for "Oktoberfest") 6-2 Upon initial review of the proposal, City staff and the consultant, IBI Group, have endorsed the overall intent proposed by S&E, with the understanding that S&E prepare a detailed work plan for technical review and dialogue with the core project team. In general, staff have responded positively to the block approach and merger of stages suggested between Young and Water Streets; as there are efficiencies in overlapping these blocks, in terms of sequencing of work and progression of project operations. For example, underground utility work will be completed in the first block or stage (1 a} and upon completion, proceed with the second stage (1 b) without delaying the project schedule. This will provide S&E with ability to complete the streetscape work without subcontractor disruption. Similar to planning process 2008-09, City staff and the IBI Group will continue to work with the downtown BIA in 2010 on finalizing the details of the project schedule and staging or work proposal. As part of this preparation, regular scheduled meetings have resumed with the BIA to review the details of this proposal and provide further insight from the local businesses community. These discussions worked well in 2009 as this dialogue helped mitigate the inconvenience of construction by increasing communication, reducing access disruptions and supporting special events throughout the course of construction. As such, City staff and the downtown BIA have emphasized the importance of meeting key milestones for special events planned in 2010. Lessons Learned Survey /Risk Registry The Engineering Services Division has adopted a lessons learned process that will be implemented at the end of a project's life-cycle. Due to the sensitive nature of King Street Reconstruction project, amid-project lessons learned approach has been completed. As part of a continuous improvement process, documenting lessons learned will help the project team to discover the root causes of problems that occurred, in hopes to; avoid similar problems in later stages of the project, improving implementation of new projects, and preventing or minimizing risks for future projects. As part of this process, a survey was posted on the City's website between January 29 and February 5, 2010, where, a preselected list of project participants l stakeholders were invited to vote and comment on a series of questions centred around the streetscape work completed in 2009. The surveyed focused on several key areas of the project, ranging from general questions about the design /scope of work to specific questions about project management and the performance of City staff, the contractor and consultant teams. The underlying objective of this survey is to build on the knowledge base gained from each group and apply this experience to further enhance engineering processes and procedures. The feedback from this process will be documented so that the knowledge can be transferred to subsequent phases of the current or future projects. Some early examples of areas for improvement include: (1) Overall City staff were quite pleased with the final product, although, it is believed that certain aspects the contractor's workmanship may have affected due to pressuring timelines and meeting key milestones eg. quality of paving stone installations and the reopening of the block to vehicular traffic. As a result, some deficiencies have been identified and will need to be rectified prior to final acceptance. Lesson Learned: The project team should spend special attention to deficient items identified in 2009 and adjust project schedules accordingly to provide sufficient time to meet City expectations. In other words, create a balance between the triple constraint model, "time, cost and qualitylscope", with added emphasis placed on quality/scope; and, 6-3 (2) It was observed that overall cost control was challenging to manage and forecast at various stages of construction, due to the method in which the cost estimates were prepared in the planning phase, prior to the commencement of construction. eg. many contract items are carried over the course of a project where, at various stages of work, are partially completed and require additional effort to validate. Lesson Learned: Cost estimates for construction should be structured to coincide with the anticipated staging of work proposed in the contract documents, thus, a `cost baseline' can be established and used as a point of reference to identify over /under estimated expenditures. The results of this survey are still being compiled and will be incorporated into the 2010 risk registry for routine monitoring and action, as necessary. Enclosed is a summary of the risk registry upon initiation in November 2008 and as last recorded in August 2009; Original Risk Assesment (November 3, 2008): Risk Rating Low 1-5 Medium 6-9 Hi h 11-15 Total (Impact x likelihood) 9 10 10 29 Last recorded Risk Assesment IAugust 21, 2009): Risk Rating Low 1-5 Medium 6-9 Hi h 11-15 Total Im act x likelihood 8 6 9 23 Note: (1)11 new risks were added since November2008totaling 40, (2)17 risks were closed during the completion of phase 1, and, (3) Risk Registry meetings to resume March 3, 2010. Project Budget In December 2007, a 60% design package and business case for the reconstruction of King Street was presented to the Development and Technical Services (DTS) Committee for its consideration. At that time, DTS Committee endorsed the 60% design and ear-marked $5.68M in capital funding for the reconstruction of King Street and Speaker's Corner. Later on February 4, 2008 the funding for the project was ratified by Council of the whole as part of the City's broader capital budget process. During the same period, a proposal was submitted to the Province of Ontario, as part of the Municipal Infrastructure Investment Initiative (MITI) program where, the City received confirmation on March 28, 2008 that King Street had been awarded a $3.2M grant. Based on this announcement, the contract documents were adjusted accordingly to reflect the increase in capital funding and the tender was released to apre-qualified list of general contractors to bid on the project. On August 27, 2009, after contract award and during construction, the City successfully secured a second grant from the Federal Economic Development Agency (FedDev). The total amount eligible under this program is $1.23M, and upon receiving confirmation, the scope of work was increased on King Street and the limits /duration of construction were extended to include the streetscape around City Hall which, must be completed by March 31, 2010. To date, the scope of work associated with this funding is approximately 80-85% complete and is anticipated to be finished on schedule. 6-4 On January 11, 2010, Finance and Corporate Services Committee (Report No. FIN-10-005), endorsed a recommendation from staff to submit an application for federal funding under the Community Adjustment Fund, intake 2 (CAF2). An application was submitted for federal funding consideration, where, King Street and City Hall l Civic Square were listed as one of the three top priorities. The total amount of this application is $0.75M and if successful, will be allocated for items that include, but are not limited to: concrete refinishing at Civic Square, paving stone crosswalks on King Street (Phase 1 &2), concrete roadways to define entrance features near Frederick and Francis Streets, concrete curbs /parking areas on Young and College Streets, and miscellaneous items, such as, street furniture, decorations and special event infrastructure. FINANCIAL IMPLICATIONS: 2009 Financial Summary (as of December 31, 20092 Ex enses King Street & Speakers Corner $3,972,533 Design, Engineering & Consulting $ 986,466 Public Art at Speakers Corner $ 79,669 Urban Vitality (the Cube) $ 115,000 LightinglTraffic Pole Procurement $ 329,256 Young & College Streets (CAF) $ 84,662 Note: Total = $5,567,586 Total = $8,480,000 Balance (Surplus) _ $2,912,414 1. Street light work completed under the Infrastructure Stimulus Fund (ISF) City Hall Lighting project is not shown above and will be reconciled at a later date. Presently, approximately $83,000 has been allocated for lighting procurement and $205,000 for street light installation on Young, College and Duke Streets; and, 2. The total contract value for construction of phase 1, King Street (Young / Gaukel Streets to Frederick 1 Benton Streets) & Speakers Corner is $4,039,821.80, of which, approximately $67,000 or 1.7% is remaining in the 2009 purchasing order and will be transferred to the project contingency for 2010-11 construction. 2011 Projected Financial Summary (upon completion): Expenses King Street & Speakers Corner Design, Engineering & Consulting Public Art at Speakers Corner Urban Vitality (the Cube) Lighting/Traffic Pole Procurement Young & College Streets (CAF) Source of Funding $7,237,880 Contribution from EDIF $3,830,000 $1,497,330 DTS Street Improvements $1,500,000 $ 100, 000 DTS U rban Design $ 150, 000 $ 130,000 CSD Downtown Parkettes $ 350,000 $ 679,130 Provincial Grant (MIII) $3,200,000 $1, 230, 200 Fed Dev G ra nt (CAF) $1, 230, 200 Tree Canada Grant $ 13,200 Cost sharing (Utilities) $ 628,140 Note: Tota I = $10, 874, 540 Total = $10,901,540 The City is pending results on a grant application submitted to the Federal Economic Development Agency (FedDev) under the Community Adjustment Fund, intake 2 (CAF2) program. If successful, a $750,000 grant would be allocated to increase the scope of streetscape work planned for King Street and City Hall in 2010-2011. Source of Funding Contribution from EDIF $3,830,000 DTS Street Improvements $1,000,000 DTS Urban Design $ 100,000 CSD Downtown Parkettes $ 350,000 Provincial Grant (MIII) $3,200,000 6-5 COMMUNICATIONS: Lessons Learned Survey: As mentioned above in the contents of the report, a survey was posted on the project website for King Street under a dedicated internet address where, a preselected list of participants were invited to vote and comment on a series of questions centred around the streetscape work completed in 2009. Participants included representatives from a number of City divisions such as; Engineering Services, Economic Development, Operations, Special Events, Arts & Culture, Facilities Management and Communications. In addition, external invitations were extended to a number of agencies outside of the City, these groups included; Consultant l Contractor teams directly working on the project, utility groups (Bell, Atria, Telus, Rogers and the Region of UUaterloo) with an invested interest in the final product, and further, the downtown business association (Downtown BIA), where, the businesses impacted by construction have had an opportunity to offer feedback and comment. The results of this survey are currently be assessed by project staff, and once completed, will be compiled and added to the 2010 risk registry for routine monitoring and action, as necessary. Communication Plan: On January 5, 2009, a detailed communication plan for King Street reconstruction was presented to DTS Committee (Report No. CAO-08-042) for information purposes. The contents of this report outlined the City's target audience(s), key communication objectives and the tools I techniques in order to achieve these goals. These techniques included, but were not limited to, weekly project meetings with key project staff, construction information briefs, business information brochures, display boards, project signage, radio / TV /newspaper ads, downtown ambassadors, Your Kitchener articles and media releases at major milestones throughout the project. As outlined in the report, the total budget for the communications on King Street was $23,000 and to date, approximately 70% of the budget has been expended. Business Attraction: In addition to the tools /techniques listed above, staff are working with the BIA on the second phase of the communication plan -Business Attraction. The City and BIA are working with MJB Consulting to develop an on-going business attraction strategy. The strategy will be aimed at filling existing commercial vacancies in the downtown, with King Street being a particular focus. The details of this strategy are work in progress, but it is expected that business attraction will commence as early as this summer, where, staff will continue to work closely with the BIA and explore additional opportunities to communicate furtherwith the public. ACKNOWLEDGED BY: Jeff Uvlllmer, Interim General Manager of Development and Technical Services 6-6