REPORT TO:
Councillor Berry Vrbanovic, Chair, and Members of the
Finance and Corporate Services Committee
DATE OF MEETING:
February 8, 2010
SUBMITTED BY:
Dan Chapman, General Manager of Financial Services and
City Treasurer
PREPARED BY:
Jaya Chatterjee, Junior Financial Analyst, Financial Planning
WARD(S) INVOLVED:
All
DATE OF REPORT:
February 3, 2010
REPORT NO.: FIN-10-022
SUBJECT:
STIMULUS PROJECT UPDATE - FEBRUARY 2010
RECOMMENDATION:
That the tenders pertaining to Infrastructure Stimulus Fund projects awarded by the
Chief Administrative Officer, be acknowledged, as set out in Appendix ‘C’ of Financial
Services Department report FIN-10-022; and further,
That the Mayor and Clerk be authorized to execute any agreements pertaining to the
tenders awarded with respect to Infrastructure Stimulus Fund projects provided said
agreements are satisfactory to the City Solicitor.
BACKGROUND:
This report is part of a series of bi-monthly updates to Finance and Corporate Services
Committee on the status of the City’s Stimulus Funding Projects. This reflects a commitment to
ensure that these infrastructure funds is spent in an open, transparent and accountable manner
and that Council is afforded an opportunity to track the progress of these projects on a regular
basis.
REPORT:
Section 1 – Project Status Update
Appendix “A” provides a summary of project status and Appendix “B” depicts the progress
towards completion of each project compared to the planned timeline. Since the previous report
(December 1, 2009) many projects have made progress. Some projects have not advanced
due to factors beyond the City’s control as discussed in this report or because of the time of
year. All projects are behind schedule to some degree, but project managers have confirmed
that each project can still be completed with the permitted time frame.
ç ó ï
The City has submitted its first claim for all the 9 ISF projects and the CAF King Street
reconstruction project for the period ending December 2009.
Section 2 – Expedited Purchasing Measures
Council has previously approved a number of purchasing measures to expedite projects
receiving funds under the Infrastructure Stimulus Program, while still maintaining a fair, open
and transparent procurement process. The measures, along with comments on their utilization,
are outlined in Appendix “C”.
Council has previously delegated authority to the Chief Administrative Officer to award tenders
on Infrastructure Stimulus Fund projects provided that the costs are within the projected
expenses outlined in the applications and they are reported to Council by way of the bi-monthly
update report. This authority has been granted to expedite projects which must be completed
under significant time constraints imposed by the Federal and Provincial governments. Legal
Services staff have indicated that while this resolution provides authority for the CAO to award
the tender, it does not provide authority for the Mayor and Clerk to sign the related agreements.
Staff have proposed a recommendation in this report to provide authority to the Mayor and Clerk
to sign said agreements.
Section 3 – Federal/Provincial Program Updates
CAF II application:
Staff submitted applications for the CAF Fund Intake II on January 18, 2010. The projects
applied for the CAF Fund Intake II are as follows:
1. Victoria Park Lake Design Phase
2. Redevelopment of Woodside Park (Synthetic Turf)
3. King Street Master Plan and Civic Square Renovation
It is anticipated that applications will be reviewed soon and projects will be announced
immediately after the assessment.
Section 4 – Other Information
RInC Application for Aquatic Facilities:
As directed by Committee, the Mayor’s office has been in frequent contact with MP’s and MPP’s
with respect to the status of the approval of the Aquatic Facility Upgrade. The City has received
verbal confirmation from Co-Chair of Joint Secretariat advising that the first four projects out of
five Aquatic facility projects have been approved. Kiwanis Pool has not been approved since the
full scope of work cannot be completed within the deadline of March 31, 2011. Written
confirmation of the approval of projects is expected within a week, followed by amendment of
RInC Contribution Agreement. Work on these projects will commence with the anticipation of
the projects to be completed by March 31, 2011. Staff will bring forward a funding
recommendation in late February or early March 2010.
The following projects were within the scope of the applications:
ç ó î
Location Scope Amount
Complete change house upgrades, deck Replacement,
Harry Class Pool Epoxy resurfacing, re-pointing, roof repair, piping $1,650,000
replacement, filtration upgrades
Filter system upgrades, complete re-piping, De-
Breithaupt Pool $350,000
humidification /Building Control upgrades
Wilson/ Kingsdale Changeroom upgrades, installation of splash pad, filtration
$500,000
Poolupgrades
Changeroom upgrades, installation of splash pad, filtration
Chicopee$500,000
upgrades
Complete Over haul: Mechanical & Electrical, surface/
Kiwanis Pool $2,000,000
structural replacement
Total $5,000,000
OPA Approval of CMF Solar Roof:
The OPA has reviewed the City’s application form in detail and has deemed the application to
be complete having satisfied all of the eligibility requirements set out in sections 2 and 3 of the
FIT Rules.
The OPA will now be assessing by order of time-stamp whether connection resources are
currently available to connect the City’s project in accordance with section 5 of the FIT Rules.
The OPA's target for processing applications in accordance with sections 5.2 and 5.3 of the FIT
Rules is 60 days following the date of response (January 7, 2010). However, due to the high
volume of applications received, more time will be required to complete this process.
The Solar PV contract for the design/construction of this project, which is out for tender, has
now been extended with a closing date of February 12, 2010 and has a 120 day award period to
allow for OPA’s timing uncertainties. With a contract award in early to mid-June and a 9-month
design/construction period, the commercial operation date is likely to be March 31, 2011.
The extension of the commercial operation date into 2011 means that new product rules will
apply. The Canadian content of the product changes from 50% to 60%. According to information
based on comments from the bidders, this should not significantly affect the project budget or
reduce the range of product availability.
The City has added a performance clause to the current tender through an addendum. It states
that if the project is not substantially complete by Feb 11, 2011 and project closed by March 28,
2011, then the City will pay only the 1/3 rd share of the cost incurred to complete the project
beyond the ISF deadline and balance of the cost will be incurred by the bidder. The addition of
the performance clause transfers the risk of completion to the contractor and ensures that the
contractor develops a realistic and aggressive schedule.
Staff has been in continuous dialogue with the OPA and has been advised that the contract
should be awarded by March end or early April 2010.
Sportsworld:
Staff has received a verbal confirmation from the project analyst indicating that the Federal
government has approved the “Cost Plus” approach (construction management) with Ball
ç ó í
Construction. The agreement with Ball Construction will be executed upon receipt of written
confirmation and construction will then be initiated.
FINANCIAL IMPLICATIONS:
The total cost of the four approved RInC projects amount to $3 million, the City of Kitchener will
be responsible for funding 1/3 of the eligible project costs totalling $1 million. Staff will bring
forward a funding recommendation in late February or early March 2010.
COMMUNICATION:
To assist in ensuring the infrastructure stimulus funds are spent in an open, transparent and
accountable manner, staff continues to implement the communications strategy that has been
developed to assist in tracking the progress of all 12 projects. The strategy contains various
communications tools that will give residents an opportunity to follow the work that is underway
on each project.
Federal and provincial signage has now been installed at all project sites, recognizing
federal and provincial funding support; only federal signage was required to be installed
for the King Street reconstruction project, as it is supported by the federal Canada
Adjustment Fund;
Project-specific web pages, featuring an interactive map showing all project sites, is
updated on a bi-monthly basis to ensure a user-friendly way for citizens to access
information on each project. The web pages include background on each project, as well
as status updates as they are provided by the project managers;
Project progress continue to be included in every edition of Your Kitchener; this process
will continue until the projects are complete; and
Media releases and/or media events are planned for the completion of each project.
ACKNOWLEDGED BY:
Dan Chapman, General Manager of Financial Services & City Treasurer
ç ó ì
ç ó ë
ç ó ê
February 8, 2010
Utilization of Council-Approved Expedited Purchasing Measures
Expedited Purchasing Measure Utilization
The Mayor and Clerk are authorized to sign ISF Contribution agreements have been
Provincial and Federal agreements as they received and executed after being reviewed by
relate to the Infrastructure Stimulus Fund and the City Solicitor. CAF letter of offer has been
the Recreational Infrastructure Canada Fund, received and executed by the City Solicitor.
subject to the satisfaction of the City Solicitor. RInC agreements have been received and
executed after being reviewed by the City
Solicitor.
The Chief Administrative Officer is designated For Bridgeport Community Centre, expression
to award tenders on Infrastructure Stimulus of interest for Consultant was awarded to
th
Fund projects provided that the costs are AECOM with CAO’s approval on Oct 20
within the projected expenses outlined in the 2009. Cost of the award is $218,925. Total
applications and they are reported to Council budget of the project is $2,249,740. There is a
by way of the bi-monthly update report. tight schedule for this project and a delay
might jeopardize the project. Province
confirmed funding for this project after a delay
of almost 2 months.
For Sewer and Watermain Rehabilitation
project, expression of interest E09-100,
Consultant Services – Rehabilitation of
Infrastructure on Selected Streets Using
Trenchless Technology has been awarded to
Conestoga-Rovers & Associates, Waterloo
th
with CAO’s approval on December 14 2009.
Cost of the award is $257,600., including a
contingency of $22,400. and G.S.T.
Consultants involved in the preliminary phases This measure has been effective at expediting
be retained and the consultant selection the project timeline.
process be waived for following projects
mentioned below:
McLennan Park – Walter Fedy Partnership
CMF Improvements - Giffels Associates
Limited/ IBI Group (Architect consulting
services)
CMF Improvements - Morrison Hershfield
Limited (Mechanical and Electrical
consulting services)
CMF Improvements - Morrison Hershfield
Limited (LEED consultant services)
ç ó é
APPENDIX "C"
STIMULUS PROJECT STATUS UPDATE
February 8, 2010
For Consultant projects over $100,000, cost This measure has been effective at expediting
information is to be included with the original the following projects:
submission, the interview process is to be
Storm Water - Infrastructure
waived, and the selection will be based on the
Rehabilitation
original submissions.
Bridgeport Community Centre –
Architect Expression of Interest
For Storm Water Infrastructure Rehabilitation This measure has been effective at expediting
projects, involving drainage upgrades only will the project timeline.
be delivered by general contractors under
existing construction contracts through a
standard change order process as per
purchasing guidelines.
That the Mayor and Clerk be authorized to This measure will expedite the project timeline.
execute a 'cost plus' agreement with Ball The City has received a verbal confirmation
Construction for the completion of the design from the Federal government on this
and construction of Sportsworld Arena approach.
improvements to an upset limit of $900,000;
said agreement to be to the satisfaction of the
City Solicitor.
The King Street reconstruction project be This measure has been effective at expediting
delivered by general contractors and the project timeline.
consultants under existing construction
contracts and consulting contracts through a
standard change order process as per
purchasing guidelines.
That the Mayor and Clerk be authorized to This measure has been effective at expediting
execute any amendments to Agreements the project timeline.
pertaining to Projects for which funding is
approved through the Infrastructure Stimulus
Fund, the Recreational Infrastructure Canada
Fund and the Community Adjustment Fund, if
necessary, and provided said amendments
are satisfactory to the City Solicitor.