HomeMy WebLinkAboutDTS-10-056 - Class EA Study, Strasburg Creek Flood Control StructureJ
KITC~i ~R ' •
De~elopment&
Technical5ervrces
REPORT T0: Development & Technical Services Committee
DATE OF MEETING: March 8, 2010
SUBMITTED BY: K. Grant Murphy, P.Eng, Director of Engineering Services
PREPARED BY: Binu J. Korah, P.Eng, Manager of Development Engineering
(519 741 2974)
WARD(S) INVOLVED: Ward # 4
DATE OF REPORT: February 24, 2010
REPORT NO.: DTS-10-056
SUBJECT: CLASS ENVIRONMENTAL ASSESSMENT STUDY FOR
THE STRASBURG CREEK FLOOD CONTROL STRUCTURE
-PROJECT STATUS UPDATE AND AMENDMENT TO THE
PURCHASE ORDER FOR CONSULTING SERVICES
RECOMMENDATION:
THAT Council approve the extension of the Purchase Order for consulting services to
Stantec Consulting Limited for the additional amount of $330,000 plus applicable taxes to
complete the Class Environmental Assessment Study, Detailed Design and Inspection
for the Strasburg Creek Flood Control Structure.
BACKGROUND:
The Strasburg Creek watershed is located in the southwest part of the City of Kitchener (City).
The main/middle branch of Strasburg Creek originates northwest of the intersection of Fischer-
Hallman Road and Bleams Road and flows generally southeast through swell-defined, well-
vegetated valley crossing Huron Road approximately 1 km west of Strasburg Road. The
drainage area contributing to the Main Branch of the Creek is approximately 3.6 km2 and 6.4
kmz at the Fischer-Hallman and Huron Road crossings, respectively.
The Strasburg Creek Master Watershed Plan (SCMWP) was completed by Paragon
Engineering Ltd. (now Stantec Consulting Ltd.) and Ecologistics Ltd. in 1991. As part of the
study, a hydrologic modelling for the watershed was completed based on assumed
development patterns and recommended a series of major on-line flood control structures to
minimize the potential for downstream flooding and erosion impacts. The Grand River
Conservation Authority (GRCA) and the City of Kitchener approved the SCMWP shortly after its
completion.
One of the primary results of the SCMWP was the recommended construction of a Flood
Control Structure, at a location just upstream of the main branch's crossing of Huron Road.
This structure is to replace the existing berm l spillway structure that has historically created the
former Battler's Pond. The function of the proposed structure is to control outflows during
infrequent storm events to minimize the potential for negative downstream flooding impacts due
to the development of the upstream catchments.
5-1
As a result of the SCMWP, the City had identified the necessity of preparing a Schedule "B"
Environmental Assessment (EA) for this project to examine alternatives for the proposed means
of providing sufficient controls upstream of Huron Road to minimize the potential for flooding
within this area.
Stantec Consulting Ltd. was retained to complete the work in 2003 (Council resolution, DTS-03-
038) and work continued until late 2003, when it was decided to wait for the updated watershed
modelling to be completed as part of the Alder/Upper Strasburg Watershed Study before
finalizing the Strasburg Creek flood control structure EA. Subsequently in 2008, the City
authorized additional work to continue the project (Council resolution, DTS-08-066).
REPORT:
The City had re-initiated the Strasburg Creek Flood Control Structure EA study in 2008, see
attached map, study area. As part of the project, a project team and a stakeholders group was
set up to inform the study findings. The project team consisted of GRCA, city staff, Region and
the consultant, while the stakeholders group consisted of all the affected landowners within the
study area.
The project team had completed the following tasks as of part of this ongoing Class EA:
• The analysis of existing conditions by undertaking field works and site walk.
• Prepare and coordinate distribution of Class EA notifications
Update computer models to incorporate the final Upper Strasburg Sub watershed Study
and Fischer-Hallman Road Culvert EA results
• Identify Project alternatives, Evaluation criteria and environmental impacts
• Public Information Centre #1 (October 28, 2008)
Coordinate design alternatives with the Huron Road Class EA project team
• Present the study findings to City of Kitchener Environmental Committee (April 16, 2009)
Meet with Ministry of Natural Resources staff to discuss the study findings to understand
their concerns and permit requirements.
The project team had considerable number of meetings with the stakeholders group, agencies
and upstream landowners. Initially 10 meetings were included in the scope of work and due to
the nature of the challenges, project team had 38 meetings so far with all the parties.
The major challenge on this project is to determine the Regional flow release rate from the lands
west of Fischer Hallman Road and at the same time satisfying the Alder Strasburg Watershed
Study targets and recommendations. The Region also has to review and agree the concept of
the recharge requirements and release rates for these lands to make sure that the Regional
wells are not adversely impacted due to the developments. The City is still working with the
landowners, GRCA and Region to complete the appropriate analysis and release rate. Staff
anticipates that several additional consultations may be required to complete this project.
The Huron Road Class EA is also progressing
incorporate flood control measures into the
Consulting Services will complete the detailed
services for the flood control structure.
concurrently with this study with the potential to
final design and construction. The Stantec
design, contract administration and Inspection
The reason for changes in the scope of work and associated costs are listed below:
1. Additional meetings -The project team has been required to attend additional meetings
to review and consider information provided by the various stakeholders. The meetings
to-date have seen progress towards a consensus for an upstream drainage strategy
required to finalize the EA. Some additional meetings are required with the
5-2
stakeholders, and further coordination for agency approvals and with the Huron Road
design team.
2. Visual Simulation - A visual simulation will be prepared to illustrate the proposed flood
control conditions. This is a useful tool for City staff and the community to assist in
general understanding of the proposed design.
3. Ministry of Natural Resources (MNR) - The MNR has now confirmed their requirements
for review of the proposed flood control structure. This criteria include the submission of
a work permit application to confirm approval of the potential location, and subsequently
a detailed dambreak assessment of the proposed structure as part of the detailed design
process.
4. Detailed Design -The original scope of work only contemplated the completion of the
EA and a conceptual design. The project now requires detailed design, final analysis
and submission of technical information to the appropriate review agencies in order to
secure the requisite approvals.
5. During and Post Construction Services -Assistance during the tendering and
construction of the flood control structure, including occasional inspection and
certification of the final product.
FINANCIAL IMPLICATIONS:
The total additional funding of $330,000 is required to complete this project. Funding is
available, Middle/South Strasburg Creek Water Course, work order # 223 (previously, Index
Code 855221), which is solely funded from the Development Charges Reserve fund.
CONCLUSION:
The Strasburg Creek Watershed Study Update and Upper Strasburg Creek Class EA have
been completed. At this time, the City would like to complete the Strasburg Flood Control EA.
Due to the scope changes to this project, staff recommend that the Stantec Consulting Ltd.
Purchase Order be increased to complete the Class Environmental Assessment study and
subsequent design and post construction services work for the Strasburg Creek Flood Control
Structure.
ACKNOWLEDGED BY: Jeff Willmer, Interim General Manager DTS
5-3
` i
~ ' ~~
,~~ ~~
~ ~ ~~- d ~ V 1~ ~1~ ~ ~ ~~
~~ ~ -~~ ~ arMry ~'4 ~~~~y~t~~~,~~~~g111 ~~'i~t~y~~~ i~~~~y~~i1r ;5~tiryry4~Y
~. l:~r~k ~~ ~~~ Pk. ~ 17i~ ~ ,`~~i1~~jlVjk~~_i~~1}j ~hl Y~~ti,~.l,'a
1 ~ ; ,~ ~ ~,
~+~ i ~ ~ ~ .~ tlVa~"j. Tr.... ~ 4 ~r - ~ ~.~~`}~l~ ii4 -~i~~.~ '~ ~ a,
~ ~ x ~ ~ ? 'ey ~ ~ia4+r"~y'.."` '- N r ~~ ~ ~ ~ ~~ "~ Y 141, ~ ~ ~ :''k }' ~ ~ '
e s^ ,, r ~ a e t ~ t 'a` ~ . ~
iL .r r ~ 9'% ti ~ ~P ~ ~
~ • ~ ~ ~F ~ ~ ~, » ,
„ h
E . j ,,,~.
` ,
y .,
{~ ~ M
s a= ~°~'~ Lr s"'i/ Y'- yyy ~ ~ .. „.i'..~.,,."r.. ' }y q ~` ,~`'~ 6}
, ~
N V~ ~ ~~
~~ ~; .^ r ,~, ,~ ~~.A"~~ >vlK~ ~ i st, "I „r shy.." v ~~}~i
r ~' ~ 7
~~. ,
n
'm"~qi
•
~~ 44
y}M1 '~h T.lp+ r rt ~ %h w rlr. 1
i~~ w,,... .. 1,ry T/
~, ~ ~ ~ - ,fir, ' ~ ~. ~ ,~ ~1l
. iR r I
r ~ .
_ '= ~ .~s
y~ , , y~
a~ - ~ ~ _ -_ ,: .,-t. . ~ ~ ~~ ~, ~" S ~ '~ .~ 7. - P ~ ~ e~ ~ ~ ,p. - fir'" ;ia5~ €ii~~"
X3;7\1h _m q y ~~"• •;~.~ o '.i _ TTY ~n~~~~ I ~I~P
r. !
" TT" L
(.~
'~ ,, .. h : ~ R ; ~ a~` - , mom' ~,~;, r 1
r+ ~~ ~ ~°.~ , ~ ~ a• fir,! r'~ ,~~~4 ~, ~ M1 r~t~~7`ir 'S`
,„
17. 4 s,~ _ ''''}} ~ ° f~ Est i ~
u
t ~ 1F r ~ ~" . ~ rr~l ~' p .h ~yprr ar" ~. ~4eP~ ""1 l ° a`~ ~~; r~' F~
r i t 4
~ '~ y ~ Ffm, ~ fr '~'~~ ~ err ~~ L 55 ~u
6 ,S' ~ ' v.0.`.
'+ j
{ ~
~~ l ~~ ~ ~ ~ ~ ' s
~7" z
"i ~` '~ ~ ^
~ , z , s ~ it ~.- +.
~ n' ~# ~ ~~
r
4,
~h..4 ~1
„
, -, " ., -
~~,t'~:, ~ w v„
I
;+ } . ,
`a" rA" 1 i ''r
~l1 o R s y.M 1 ~ p i
r
sky'. ?, :+r'~r r 3 ~ ,7^x 'a ,,iF_- ~'." ? ~ ~ i 5 ~ - ~. ..#
1
't ~ 4 A~ ~ "jt~.I e '1
a,~ ~~{i ., r_ x~' k~ gyp` "~"~* ~i'~.' ~ p R. « k -
~~ U" ~t ~ 4 - + ~ h ~~ a
~ y N ~ 7
" '.., ,,
• !' ~ ~'2 R k`
~: ~, 4r'
~ f ~ ~ ~ ~ ~ ~
3 •[
r ~ ~~ ~;~~ `'~ vim,,. ~$ ~ ~ ~ ~ ~~ . '~ .~ ~ y ~ ~ '9i'' '~ 3 s 1, 1 ~.
+,
~~
~ ~_,
~ '~
".
~ ~ _~ '
~-
a ~" ~ }~~": ~ - r ° '~ 'fin ~'t r , >, "
,~ .n + ~4 '`'-}a1 a~tyr ~ ~.-~ ' ~ ~~ ~~*~.y~`, qs "s~A,, .' n~ u~'. ~'~, i~fi ~y i:l ~ ~ l
7 ~ i"t- ~a ~ r ~ u ~ y
`~' ~~ ~* ~., ~ j ..~ ~3° ~ 1 as:,$~. ~'y ,~ ~ y ~'~ ~'" ~+~ .~ ~ f ^~ 1 .' 1 5R g k " a , .1 ~ ~ ~,. eM1;,~ ~
~~ ~1 .~~ "* hew 1'rh e ", ~~ .~''I ~ ~, ~ ~. ~" .'~ wq, 1~n. " ~' ",y~ ~~ ,,y ~' ~~. ~ r
,. ~ ;~, ;err *+ .~,~ 5a~ w +pe ~ ~ ro .~" !}? `~ ~• r~
° ~ ' x ,, y ~ ~ ~~ ~ ~* ,rte' ~ ~ ~ L
_~ I i ~' y b fit, ,,~ .,h ~ a ~~ ~ ~ ~ ,~ w `• ~n ~~r, kryN ~ , '', \~ '' f , ~' 2•." ,
r
v ~ `~-. ~ '- ~ ~ r ~ `- 7,: ~~k i a .4 a A, '". ~ s~ ~ W~ mT3,~~'~ ~4 ~ ~
. _ -
~ .. :.
~, ;~ ~ ~ ~"' wh ~,~ ~ '~ ; 4 ~ 'fie ,~'~ , b~~ l~ '
..,
o~ ~ ,, y 5
4