HomeMy WebLinkAboutCAO-2023-231 - 2023 Business Plan - April Progress Report www.kitchener.ca REPORT TO: Community and Infrastructure Services Committee DATE OF MEETING: May 15, 2023 SUBMITTED BY: Kathryn Dever, Director of Strategy and Corporate Performance 519-741-2200 ext. 7370 PREPARED BY: Justin Watkins, Manager of Corporate Planning, 519-741-2200 ext. 7203 WARD(S) INVOLVED: ALL DATE OF REPORT: April 27, 2023 REPORT NO.: CAO-2023-231 SUBJECT: 2023 Business Plan April Progress Report RECOMMENDATION: For information. REPORT HIGHLIGHTS: The purpose of this report is to present the 2023 Business Plan Progress Report as of April 30, 2023, consisting of 29 projects in total (Attachment A). Since the January update, one strategic plan action has been completed and all remaining seven actions remain on track to meet expected completion dates. Of the 16 business plan projects endorsed for 2023, 15 are on track to meet expected completion dates and one project is delayed. There are no financial implications arising from this report. Community engagement included in advance of the committee meeting. This report supports BACKGROUND: The 2019-2022 Strategic Plan includes measurable, specific actions with a timeline for completion, and a commitment to measure and report on progress to Council and the public throughout the life of the plan. The annual business plan includes strategic plan actions and other high priority business plan projects identified by Council and staff, and progress is reported three time per year. REPORT: Status of Ongoing Strategic Plan Actions As illustrated below, one action in the 2019-2022 Strategic Plan has been completed during this update period, and all remaining seven actions are on track to meet expected completion dates, *** This information is available in accessible formats upon request. *** Please call 519-741-2345 or TTY 1-866-969-9994 for assistance. as of April 30, 2023. The action completed during this reporting period was the Bikeshare Program project. Of the remaining seven actions, five will be complete by the end of 2023. The remaining two actions Protected Cycling Network Connected to the Downtown; and Open Space Strategy + Equitable Facility Distribution will be completed in 2024 and 2025 respectively, as previously reported. All full summary of strategic actions and status updates can be found in Attachment A. Status of Business Plan Projects The 2023 business plan was endorsed in January of this year and consists of 16 projects. As of April 30, 15 business plan projects are reported as on track to meet the expected completion date and one project has been delayed to 2024. All full summary of business plan projects and status updates can be found in Attachment A. STRATEGIC PLAN ALIGNMENT: This report supports FINANCIAL IMPLICATIONS: Capital Budget The recommendation has no impact on the Capital Budget. Operating Budget The recommendation has no impact on the Operating Budget. COMMUNITY ENGAGEMENT: INFORM council / committee meeting. PREVIOUS REPORTS/AUTHORITIES: CAO-2023-020 2022 Business Plan Year-End Progress Report and Recommended 2023 Business Plan Project List APPROVED BY: Dan Chapman, CAO ATTACHMENTS: Attachment A 2023 Business Plan Progress Report as of April 30, 2023 1 and , with soft to scooter - diverse o be agreement up markets and - bike and e license earlier this year - expected t taff from the Region The phase three on Margaret an e for , and s closely with Neuron April, with a full launch planned - or of ed Street is underway with a amenities, such as seating, Progress Update mid an exciting schedule of signed has was on the street throughout the spring. ecreational the service R going and showing promising ridership numbers. - three cities work May. Through an RFP process, Neuron Mobility has been selected as the operatshare system in the Region. with Neuron thelaunchfor Construction has begun Avenue and Otto Street and is completed in the fall of 2023. Detailed design for the final phase on Duke construction target of spring 2024. Data collection recently completed in the Downtown Cycling Network is onNew shipping containers for popevents arrived on Gaukel Streetartists making plans to animate the containers and the street. planters and a play space have been procured and will be installedGaukel Street events in the coming year. Status On TrackOn Track Completed 343 202202202 Completion April 30, 2023 ) dates as of Project Manager Ivan Balaban Transportation Services Darren Kropf Transportation Services Darren Kropf Transportation Services completion First Plan to the - 2025 - Progress Report Project 2023 ( Bikeshare Program Implement a bikeshare service in which bicycles are made available for shared use to the public in an effort to adfollowing a feasibility study to determine the most appropriate system.Protected Cycling Network Connected to the Downtown Install a continuous and protected cycling network that connects adjacent neighbourhoods downtown by 2022.1.5.1 Pedestrianfor Gaukel Street Develop plans to prioritize pedestrians over other travel modes on Gaukel Street. Business Plan 2023 Friendly Transportation - first streets Transform how people move through the city by making the transportation network safe, convenient, comfortable and connected. - Statement Strategic Plan Actions : : 1 oal Strategic Plan Action People G Encourage and incentivize Install a continuous and Develop a plan to create art 1.2 alternative modes of transportation by developing and subsidizing a bikeshare program by 2021. 1.3 protected cycling network that connects adjacent neighbourhoods to the downtown by 2022.1.5 pedestrianbetween Victoria Park and City Hall and P 1. Appendix A: 2 . The was . est planned W was held in at 44 Gaukel implications niversity of on the design of a waiting list U was presented to report is in late March owned properties A 2023. - the oriented art, planters for - June opening and now has determining any Innovation Arena The Creative Hub and great places to live. . Food Incubator 3 are ceremony Progress Update Progress Update passing of Bill 23. to Council in Health % leased Staff in 202 . business cases will be prepared for Council 100 with the facility breaking - nd leased space within the Arena. Construction - a taff continue to work with UW Procurement for streetnew incubation space at 2 King Street , S . progress aterloo (UW) currently groundcomprehensive review of all City A WAprilthe Cityof the completedbusiness model for athe Economic Development Advisory Committee in Marchconsiderationis Ais in as a result of the to be presented Eby Street is ready to welcome Market days and events in May with the scheduled installation of flexible swing gates to facilitate frequent opening and closing of the street. and furniture is underway to further animate the space. Status Status On TrackOn Track On Track 3 2023 2023202 Completion Completion Project Manager Cory Bluhm Economic Development Brian Bennett Economic Development Project Manager Darren Kropf Transportation Services First - owned - tech industry Kitchener - Project how they could be Project Working Space cturing and - Owned Property Review - 1.5.2 PedestrianStreet Plan for Kitchener Market Develop plans to prioritize pedestrians over other travel modes between the Kitchener Market ION station and Market.3.2.2 Incubator, Accelerator and CoNetwork Lease all spaces in the Creative Hub, explore the potential to facilitate a Food Incubator with a business case pending, and explore partnerships for the development of manufahealth/medincubators. City Complete a comprehensive review of cityproperties by 2020 to determineeffectively used to advance city strategic objectives. . owned - tech industries - StatementStatement Build a vibrant city by making strategic investments to support job creation, economic prosperity, thriving arts and culture, : 2021 for the food Strategic Plan Action Strategic Plan Action h/med - oal wide network of Foster the creation of a Complete a comprehensive - Vibrant Economy G working spaces by - between the ION and Kitchener Market by 2022.3.2 cityincubators, accelerators and cocompleting the buildout of 44 Gaukel in 2019, advancing work on a Creative Hub and undertaking business cases in 2019manufacturing and healt 3.4 review of cityproperties by 2020 to determine how they could be effectively used to advance city strategic objectives. 3. 3 . rt , the of 2023, . has been with a , engagement , with a repo s Civic District the third quarter will develop draft . . in Charles Street Terminalexisting Group community owned land plan is being developed - . Health Innovation Arena to Council W Broad Working Progress Update anticipated to start in 2023 he T the second and third quarters . expected the second quarter of 2023 biweekly working sessions throughout anticipated in June 2023 as noted above vision is underway with significant public in City staff continue to assess options for engagement Downtown Community Working Group w being incorporated into the Growing Together a community engagement Theengagedfirst quarter of 2023.on a new input receivedprinciples in presentationThe City is currently working with the Region on redevelopment of the former lands.affordable housing on Cityto Council Awith Development of the Ucontinues Staff anticipate reviewing the Master Plan in with any necessary changes to the Official Plan/Zoning Bylproject led by the Planning Division Status On TrackOn TrackOn Track 202320232023 Completion Project Manager Darren Becks Economic Development Brian Bennett Economic Development Brian Bennett Economic Development Cory Bluhm Economic Development owned - t opportunities, Project Owned Property Brought - 3.5.1 Downtown Vision and Cityto Market Develop a vision for downtown Kitchener and continue to position downtown Kitchener as a leading destination for redevelopmenwith one new cityproperty brought to market by 2022.3.5.2 Innovation District (Bramm Yards) Master Plan Finalize the Innovation District (Bramm Yards) Master Plan by 2022.3.5.3 Civic District Master Plan Finalize the Civic District Master Plan by 2022. s) Master Plan by Statement owned property - Strategic Plan Action Develop a vision for 3.5 downtown Kitchener and continue to position downtown Kitchener as a leading destination for redevelopment opportunities, with at least one new citybrought to market by 2020. Finalize the Innovation District (Bramm Yard2021 and the Civic District Master Plan by 2022. 4 and ͵ 000 staff , . through to required and April 17 are expected later a deliberate, on and over 2 , continuing completed Business Case was going - 23 and is , through building approach - on is law and policy An addendum to Spaces - of Bill . has been Progress Update & supporting our diverse populations & lan p relationship Engagement and the passage . have provided input moved into the design stage with the Catholic ngagement 2023. - The Mill Courtland Expansion presented and approved by Council An ehave District School Board.park and open spacesamendments to the byfollowing this yearquality of park and open spaceslatepeople inclusive, Status On TrackOn Track Completed ion 5 20232022023 Complet er & Project Manag Mark Hildebrand Neighbourhood Programs & Services Mark Hildebrand Neighbourhood Programs & Services Mark Parris Parks Cemeteries needs assessment Project ll Courtland complete a needs 4.4.1 MiCommunity Centre ExpansionBusiness Case Complete a and business case to determine the requirements for an addition to the Mill Courtland Community Centre.4.4.2 New Rosenberg Community Centre/SchoolBusiness Case With the Catholic School board, assessment and business case to determine the requirements for a joint community centre/school in the Rosenberg area. 4.4.4 Open Space Strategy Develop an open space strategy to explore the value of open spaces, how they function, are planned, maintained, and managed, and including a review of permitted uses in parks. Statement : Strategic Plan Action oal Caring Community Better utilize existing G helping to make housing affordable. . 4.4 facilities, provide relevant programming at community centers, and support equitable distribution of leisure programs and resources across neighbourhoods. Start work on the Mill Courtland Community Centre expansion by 2020and the Rosenberg Community Centre by 2021. Complete an Open Space Strategy by 2021. 4 5 . 3 from s . and the e ing an ) , directions for and result Bloomberg commenced interviews, focus ncluding - i Waterloo , ,strategic one - economic analys A draft plan will be one ( the fourth quarter of 202 opportunities, the , along with the will inform , Progress Update findings Bloomberg initiative - the 2023 Budget, Council allocated underway outcomes and rts and Culture Plan. ngagement In collaboration with CambridgeRegion of Waterloo, Environics has stakeholder consultation groups and an online engagement platformEHarvard currently the Apresented to Council in As part ofadditional funds to support initiatives the Harvardinventory of resources, practitioners for local artists. Status On Track ion 2023 Complet er Project Manag Emily Robson Economic Development - - Project Arts and Culture Plan Develop a new and inclusive Arts and Culture Plan by engaging a broad crosssection of the community including the arts and creative industry sector and multicultural communities. - - Statement Strategic Plan Action Engage a broad cross 4.5 section of the community including the arts and creative industry sector and multicultural communities to develop an inclusive arts and culture Plan by 2021. 6 - ; a er in s and June. main floor ext steps in N provided this work, consultantenergy planning e. a management new appointment and advisory committee for (GRAAC) nergy The staff . in the temporary service centre new business processes / was completed by to oversee e to oversee carbon launch and accessibility considerations. U Progress Update Corporate Leadership Team Progress Update carry over to the new centr demand American Sign Language - was completed report was circulated to City and School Board n . A wayfinding study recommending O . and will wayfinding, tools has been hired draft , , with a final report still to be submitted. a senior strategist 2023 anager staff review of the report to determine if there is a feasible queuing and a m with members of the public and GRAAC before summer entory, forecast, and setting renewed emissions reduction targets and River Accessibility Advisory Committee roject xpected to go to tender in late April with construction anticipated to ecommendations will go to Ebegin signage and locations for queuingrGrinput on signage, testingbooking/is working on operating proceduresplanning for movesinterpretation is scheduled to by summer staff in Augustinclude recommendation to bring forward to senior leadership at the City and School Board. To develop the next Corporate Climate Action Plan (CorCAP 2.0), staff are renewing the Federation of Canadian Municipalities Partners for Climate Change Program by completing a corporate emissions invfor 2030 and 2050 from the 2016 baseline. To support pfacilitiesin Kitchener Utilities. The Terms of Reference for the Climate Change Status Status On Track On TrackOn Track ion 4 3 202 2023202 Completion Complet - by Department King Project Manager Project ManagerJana Miller Corporate Customer Service Patrick Sport Anna Marie Cipriani AdministrationDevelopment Services Emissions end work - ) Business Plan Projects person services at - downtown core. City of Kitchener met the Status of : Development Services New Greenhouse Gas Reduction Target(s The previous Corporate Climate Action Plan (CorCAP) target of 8% absolute GHG reduction. Through this new project, a new/next generation CorCAP will be developed. 2 Community ServicesCity Hall Customer Service Counter Centralize all inCity Hall to one service counter located on the main floor, including the addition of a backarea to provide customer service support. Cameron Heights Pool Feasibility Study Collaborate with the Waterloo Region District School Board to determine the renovations and estimated costs to isolate the pool operation from the school operation to preserve a recreational asset in the art P 12 3 7 data will be law and to - In January to include ousing on next . h Business renoviction onsultant nitiatives I in March bjectives direction ffordable 2023, staff will provide a Project work is now party c - and ollaboration with trategic c A consultant has been S the next corporate climate and seek as revised to assist with w A third andiddle for ŷĻ ƦƩƚƆĻĭƷ ĻƓķ ķğƷĻ ŷğƭ ĬĻĻƓ the City senior leadership m ͵ reduction modelling completed in this project. Council ) Accounting and Corporate . to issing lanning and P GHGm underway. Progress UpdateProgress Update A is as ( the pdate In the second quarter of g u to were held with d inform next steps s availability for oning , to zwill delay starting reenhouse provide session on April 24. the second quarter of 2023 g . and financial modelling for a rental replacement by (SAP) , ch, esource was the plan . of r and the work is underway Mar nclusionary pdate ommittee xpected to begin planning for 2024 nd Environment Advisory Committee aclimate actionand review December 2022actionA project charter has been developedcommunity stakeholders retained in gatheringother displacement tools. uCan isteps management plans (including Water) have been completed and engaged to assist in the development of a detailed asset managementplan Lack Solutionse Status Status Delayed On TrackOn Track 3 2024 2023202 Completion Completion ou Project Manager Garett Stevenson Planning Helen Fylact Legislated Services Project ManagerTom Margetts Asset Management & Business Solutions Lisa Dueck term - - help comprehensive review ss lodging house bylaw, Development Services Rental Housing Studies Undertake a of tools available to increase supply of all forms of rental housing, preserve existing rental housing supply, and review supports/tools for current tenants facing relocation. This work will consider and run parallel with the inprogrepolicy, and process review which includes the review of shortaccommodations and other property rentals. The Rental Housing Studies willimplement the City's Housing For All Strategy.Financial ServicesAsset Management Planning Develop and publish two key asset management plans for Facilities and Water categories to support adherence to O. Reg 588/17 Concur Invoice Automation Invoice management solution to fully digitize AP processes. Includes 4 56 8 ) will (tax and utility receivables expand POS to Miscellaneous 2023. to with project miscellaneous . options to begin using the new system centralized customer service at the end of March 2023. It is e for continues, . for Revenue division budget includ . Intent is (POS) Progress Update integration invoicing feature end ssessing requirements and potential solutions for - - of the new solution back for this project occurred with the goal of providing Future planning will s seamless available to all customers by the end of April soft launch ĻǣƷĻƓķĻķ Ʒƚ ЋЉЋЍ ğƓķ Ǟźƌƌ ĬĻ ƩĻƦƚƩƷĻķ ğƭ ƭǒĭŷ źƓ ƷŷĻ ƓĻǣƷ ƭƷğƷǒƭ ǒƦķğƷĻ͵Staff are currently areplacement of Point of Sale customers. Business Licensing, Building Permit, Planning and Receivablewith Implementation completion expected in 2023for the development of the 2024 Aexpected that the ebe Status On TrackOn TrackOn Track 3 20242023202 Completion Project Manager Financial Operations Brenda Johnson Financial Operations Saleh Saleh Revenue Debbie Andrade Financial Planning& Reporting Saleh Saleh Revenue house - options for mail. - invoices for - voices by e billed through invoices for Miscellaneous - Financial Services invoice capture, tracking, approvals and enhanced reporting for spend analysis. Point of Sale and Expansion of Payment Options Replace the existing Point of Sale system, which is past its life cycle, and expand payment various services.Budget System Implementation Replace the existing Budget System, which was developed inmore than 20 years ago, with an external software solution.EReceivables Customers are frequently requesting eMiscellaneous Receivables which represent services that are financial system (SAP). Examples of services miscellaneous receivables include Direct Detect for alarm monitoring, Parking and Cemetery sales. Property tax and utility accounts are not included in miscellaneous receivables. Completion of this project will allow customers to receive in 789 9 . the the the ill focus planting ating delivery for ntrance to e Prime and will include spring projected to be ailouts will be setting up the M The on private property This project associated with the with . currently evalu Delivery (IPD) Duke Street start the demolition of risks of Record and the then Duke Street entrance will be staff are itect is assisting from fall planting season which w Schlegel Park City with a final selection . Progress Update at RBJ (Colliers) Integrated Project Young Street. share the financial and focuses on replacements with some infill roposal P 5 IPD team 10 will be targeted in fall planting to Kitchener, Arch t is expected the or to fto . The contractor will the team is finishing up work bed and continue waterproofing operations from , and i May from equest in Wards 1 R Wards 6 An IPD consultant planter in late spring. Green Solutions program partners have completed their has started planning for the eepeep ndoor recreation complex The contractorCollege StreetcompletedraisedDuke Street entrance to The City is undertaking anicombines the City of contractor as aproject. team and submissions made Rassessments for spring planting with 40 consultations completed and an anticipated 50 trees being planted this springRon neighbourhoods with lowest canopy coverage. initiated in the coming months within targeted neighbourhoods. Contracts are being finalized now for the spring City tree planting program which includes approx. 400 street trees. will target planting. approx. the same number of trees planted in parks and on streets. Track Status On TrackOn On Track ion 3 20220252023 Complet Project ManagerChris Campbell Facilities Management Steve Kurevija Facilities Management Josh Shea Parks & Cemeteries eep construct an indoor Construction Phase 1 and spaces. trees lost through EAB, Implementation Infrastructure ServicesRehabilitation of City Hall Outdoor Spaces Phase 2 Complete construction associated with the rehabilitation of City Hall Outdoor Indoor Recreation Complex at RBJ Schlegel Park Design & Construction Design and aquatic and turf facility at RBJ Schlegel park utilizing the Integrated Project Delivery Method.Sustainable Urban Forest Strategy (SUFS) Continue to implement the SUFS by providing grant funding to RGreen Solutions to partner on private tree planting and stewardship and planting 400 trees in parks before the end of 2023 to replacestorms and other events. 101112 10 design term - the 2023 to pavement in is anticipated for the due tatistical information s The tender for Team consultant Lees and rovide p tracking to open od Parks are under construction is nearing completion, with the cemetery spring 2023. in the process of being awarded. Work Oaten/ Idlewood and Kinzie Parks late continue to Progress Update with the for the development of the long onstruction c going for review by the Project - . Cemetery staff are on Brubacher and Westwo general information Schlegel Phase 2 iscussions RBJ washroom and Operations building season. The outdoor sports courts will be delayed quality and required corrective actions within workable weather conditions. with completion expected in Alpine/Vanier/Traynor Parks is will begin in late spring 2023. is being finalized with an anticipated tender release in spring 2023. DAssociates. and cemetery strategyThe WIP Project Team is working with the Project Advisory Team to plan the WIP Infrastructure Tour for June and to finalize the combined utility rate that will be brought forward through the WIP Report. A first draft of the report end of April 2023. rack T Status On TrackOn On Track ion 3 20220242023 Complet Project ManagerAshley Visneski Parks & Cemeteries Trisha Bradshaw Parks & Cemeteries Bu Lam Sanitary & Stormwater Utilities , - (WIP) to to guide 2017 and , and ensure the long term maintenance phase 2, Westwood - , to ensure continued ) social and environmental burial sites. Cemeteries Strategy a better understanding of . a e reat Infrastructure ServicesImplementation of Significant Parks Projects Complete construction of RBJ Schlegel Park Park and Brubacher Parks. Tender and award work at AlpineVanier/Traynor/Wilson and Shoemaker Parks. Initiate engagement at Oaten/Fergus/Idlewood and Kinzie Parks. Cemeteries Strategy Cprovide spatial, funding and community member needsterm fiscal,sustainability of cemetery services over the next 25 yearsthe future operations, care, and cemetery Water Infrastructure Program Undertake an assessment of the Water Infrastructure program originally completed in review for the next 5 years. This will inform the longand renewal strategy for water infrastructure (water, sanitary and stormwatersafe, reliable and efficient service delivery 131415 11 road Progress Update 49.99M of eligible expenditures have been $ r the detailed design phase of eight new stormwater the projects and Shoemaker Creek and Montgomery Creek 9M of $ To date, claimed. The Environmental Assessments for Schneider & Shoemaker Creek and the Rehabilitation of the Bridgeport Dike are underway. Engagement with the community and consultation with First Nations Rights holders fomanagement facilities and nine infrastructure protection projects (in creeks) is progressing well. Storm infrastructure within several reconstructionare complete. Status On Track ion 8 202 Complet Project ManagerNick Gollan Sanitary & Stormwater Utilities advance the Infrastructure ServicesImplementation of the Federal Disaster Mitigation and Adaptation Fund (DMAF)Plan and execute stormwater management infrastructure projects across the city to leverage the DMAF grant funding and implementation of the 2016 Integrated Stormwater Management Master Plan. 16